Lift Station 39 Force Main Replacement (SSO)

Funding

Budget Expenditures
Encumbrances Budget Remaining
Fiscal Year 13-14
$202,450
$27,575


Fiscal Year 14-15

$173,664
$731

Total
$202,450
$201,219
$731
$500

Project Description
The Lift Station 39 force main runs parallel with South Broadway on the west side of the road 2,600 feet from Lift Station 39 at North Shady Lane to a manhole at the corner of South Broadway and Fairfield Lane. The force main is cast iron over 50 years old and has failed several times in recent years, causing waste water to overflow into the adjacent right of way. The cast iron pipe will be replaced with polyethylene pipe.

Future Operating Impact
This project is a replacement of a current force main. Savings in maintenance costs will be realized with a newer system.

First Quarter FY 14-15
Project is complete.