Funding
Fiscal Year 14-15
|
$40,000
|
$15,313
|
|
|
Total
|
$40,000
|
$15,313
|
|
$24,687
|
Project Description
Material cost for city crews to replace non-functioning water main valves.
Future Operating Impact
This is an annual replacement project, so there is not impact on future operational costs.
First Quarter FY 14-15
Valve replacement underway. Will continue through the year.
Second Quarter FY 14-15
City-wide, 17 water distribution valves have been replaced so far.