Concrete Street / Inlet Repairs

Funding

Budget Expenditures
Encumbrances Budget Remaining
Fiscal Year 13-14
$100,000



Fiscal Year 14-15
$150,000



Total
$250,000


$250,000

Project Description
This project includes removal and replacement of deteriorated concrete slab sections and materials testing at the locations listed below budget permitting. When these locations require replacement for the inlet, they will be replaced at the same time as the street section. Staff envisions award of the contract late FY14 with the authorization of the FY15 budget combining FY14 ($100,000) with FY15 ($150,000) funds.
  • North 12th – 500 Sq Yd.
  • Cottonwood – 1750 Sq. Yd.
  • Ashton Lane – 900 Sq. Yd
  • Old Hickory – 400 Sq Yd.
  • Carlow – 400 Sq. Yd.
  • Quiet Hill – 500 Sq. Yd
First Quarter FY 14-15
Project awarded for $250,000. Brooks Concrete to begin construction upon completion of the D Street Ditch concrete lining project (146 to 8th St.)

Second Quarter FY 14-15
Delayed for the N. 12th water main replacement. The water main and services will be complete in April with demolition of N. 12th concrete to be removed and replaced to begin soon after.